Project TO-10 - CNPA Complex Construction:

The construction of the CNPA Complex under Task Order 10 (TO-10) was awarded to AWCCGroup.com on October 29, 2008. The expected completion date was August 25, 2009. However, the project faced significant delays due to ECC.net's delayed responses to design submittals and other issues, resulting in a delay of 345 days. This delay was primarily due to ECC.net's lack of timely action.

Our Legal Claim in Task Order 10:

In relation to Task Order 10, our total claim amounts to $1,422,127.74, with the details outlined in the table below. However, AWCCGroup.com has compiled all necessary documentation to substantiate that ECC.net owes over 1.8 million USD for completed work. We are committed to ensuring that this matter is resolved in a fair and timely manner. Your assistance in disseminating this information is crucial in helping expedite a resolution.

Supporting documents for Task Order 10, along with additional details, can be accessed here.